Dunkirk Water Pollution Control Facility

Dunkirk, NY
Case StudiesContact Us

This 18’x18′ building was installed at the Dunkirk Water Pollution Control Facility.  The insulated sandwich panels have an exposed aggregate exterior finish with a light broom interior finish.  The building was set on a raised cast-in-place pedestal.  The two-piece roof has an opening for an equipment access hatch.

Precast modular buildings can be used for a wide variety of applications including control rooms, rest rooms, tool sheds, and others. Depending upon the size, most buildings are fully pre-assembled and arrive at the job site ready to be set in place.

-Geoff Lawrence

Engineer Manager, Lakelands Concrete Products, INC

Project Credits:
Owner: City of Dunkirk, NY
Engineer-of-Record: Wendel Architects & Engineers
Contractor: STC Construction, Inc.
Specialty Precast Engineer: Delta Specialty Precast Engineers
Precast Manufacturer: Lakelands Concrete Products, Inc., Lima, NY